HARMONY MEADOWS TIMELINE
HARMONY MEADOWS TIMELINE
Timeline for Harmony Meadows Project (54 Homes)
Project Start Date: October 2024
Phase 1: Planning and Land Acquisition (Oct 2024 - Mar 2025)
October 2024:
Initiate project planning and detailed engineering.
Hire project management and engineering teams.
Conduct initial site surveys and assessments.
November 2024 - January 2025:
Finalize architectural designs and blueprints.
Secure necessary permits and approvals from local authorities.
Plan and schedule construction phases, considering monsoon seasons.
February - March 2025:
Prepare the land for construction.
Set up temporary on-site facilities for construction teams.
Begin purchasing adjacent land to expand the project to 18 acres.
Phase 2: Site Engineering and Infrastructure Development (Apr 2025 - Aug 2025)
April - August 2025:
Develop main roads within the property.
Install water pumps and establish water supply systems.
Set up electric house and power supply units.
Lay sewage lines and water drainage systems.
Plot the land for 54 homes and common areas.
Phase 3: Civil Construction for Phase 1 (10 Homes) (Sep 2025 - Jun 2026)
September 2025 - June 2026:
Construct the foundations for the first 10 homes.
Build the structural framework for each home.
Complete civil work including walls, roofs, and exterior finishes.
Phase 4: Interior Construction and Finishing for Phase 1 (10 Homes) (Jul 2026 - Jun 2027)
July 2026 - June 2027:
Install interior fixtures and fittings (plumbing, electrical, carpentry).
Paint and finish interiors.
Install kitchens, bathrooms, and other essential facilities.
Ensure each home is equipped with renewable energy solutions.
Phase 5: Landscaping and Farming for Phase 1 (10 Homes) (Jul 2027 - Mar 2028)
July 2027 - March 2028:
Develop landscaped gardens and walking paths.
Implement permaculture farming practices.
Plant trees such as teak, sandalwood, bamboo, and other native species.
Establish community orchards and vegetable gardens.
Phase 6: Final Inspections and Handover for Phase 1 (Apr 2028 - Sep 2028)
April - June 2028:
Conduct final inspections and quality checks.
Ensure all systems (water, sewage, power) are fully operational.
Finalize any remaining construction or landscaping tasks.
July - September 2028:
Handover completed homes to management team and new owners.
Set up property management and maintenance teams.
Conduct final walkthroughs with new homeowners and address any issues.
Phases 7-12: Repeat for Subsequent Phases (10 Homes Each)
Phase 7: Planning and Preparation for Phase 2 (Oct 2028 - Mar 2029)
Phase 8: Site Engineering and Infrastructure Development for Phase 2 (Apr 2029 - Aug 2029)
Phase 9: Civil Construction for Phase 2 (Sep 2029 - Jun 2030)
Phase 10: Interior Construction and Finishing for Phase 2 (Jul 2030 - Jun 2031)
Phase 11: Landscaping and Farming for Phase 2 (Jul 2031 - Mar 2032)
Phase 12: Final Inspections and Handover for Phase 2 (Apr 2032 - Sep 2032)
(Repeat these phases for subsequent phases until 54 homes are completed.)
Final Summary Timeline
Phase 1-6:
Planning and Land Acquisition: Oct 2024 - Mar 2025
Site Engineering and Infrastructure Development: Apr 2025 - Aug 2025
Civil Construction for Phase 1: Sep 2025 - Jun 2026
Interior Construction and Finishing for Phase 1: Jul 2026 - Jun 2027
Landscaping and Farming for Phase 1: Jul 2027 - Mar 2028
Final Inspections and Handover for Phase 1: Apr 2028 - Sep 2028
Phase 7-12 (Repeat for each subsequent phase of 10 homes):
Planning and Preparation for Phase 2: Oct 2028 - Mar 2029
Site Engineering and Infrastructure Development for Phase 2: Apr 2029 - Aug 2029
Civil Construction for Phase 2: Sep 2029 - Jun 2030
Interior Construction and Finishing for Phase 2: Jul 2030 - Jun 2031
Landscaping and Farming for Phase 2: Jul 2031 - Mar 2032
Final Inspections and Handover for Phase 2: Apr 2032 - Sep 2032
Key Milestones
October 2024: Project initiation
April 2025: Start of site engineering
September 2025: Break ground on the first homes
July 2026: Start of interior construction for Phase 1
July 2027: Start of landscaping and farming for Phase 1
April 2028: Final inspections begin for Phase 1
September 2028: Completion and handover for Phase 1
Completion of Full Project
October 2024 - September 2035: Completion of all 54 homes
By following this structured timeline, Harmony Meadows will be developed efficiently and sustainably, ensuring a smooth transition from planning to completion while meeting all environmental and regulatory standards.