HARMONY MEADOWS TIMELINE

HARMONY MEADOWS TIMELINE

Timeline for Harmony Meadows Project (54 Homes)

Project Start Date: October 2024

Phase 1: Planning and Land Acquisition (Oct 2024 - Mar 2025)

  • October 2024:

    • Initiate project planning and detailed engineering.

    • Hire project management and engineering teams.

    • Conduct initial site surveys and assessments.

  • November 2024 - January 2025:

    • Finalize architectural designs and blueprints.

    • Secure necessary permits and approvals from local authorities.

    • Plan and schedule construction phases, considering monsoon seasons.

  • February - March 2025:

    • Prepare the land for construction.

    • Set up temporary on-site facilities for construction teams.

    • Begin purchasing adjacent land to expand the project to 18 acres.

Phase 2: Site Engineering and Infrastructure Development (Apr 2025 - Aug 2025)

  • April - August 2025:

    • Develop main roads within the property.

    • Install water pumps and establish water supply systems.

    • Set up electric house and power supply units.

    • Lay sewage lines and water drainage systems.

    • Plot the land for 54 homes and common areas.

Phase 3: Civil Construction for Phase 1 (10 Homes) (Sep 2025 - Jun 2026)

  • September 2025 - June 2026:

    • Construct the foundations for the first 10 homes.

    • Build the structural framework for each home.

    • Complete civil work including walls, roofs, and exterior finishes.

Phase 4: Interior Construction and Finishing for Phase 1 (10 Homes) (Jul 2026 - Jun 2027)

  • July 2026 - June 2027:

    • Install interior fixtures and fittings (plumbing, electrical, carpentry).

    • Paint and finish interiors.

    • Install kitchens, bathrooms, and other essential facilities.

    • Ensure each home is equipped with renewable energy solutions.

Phase 5: Landscaping and Farming for Phase 1 (10 Homes) (Jul 2027 - Mar 2028)

  • July 2027 - March 2028:

    • Develop landscaped gardens and walking paths.

    • Implement permaculture farming practices.

    • Plant trees such as teak, sandalwood, bamboo, and other native species.

    • Establish community orchards and vegetable gardens.

Phase 6: Final Inspections and Handover for Phase 1 (Apr 2028 - Sep 2028)

  • April - June 2028:

    • Conduct final inspections and quality checks.

    • Ensure all systems (water, sewage, power) are fully operational.

    • Finalize any remaining construction or landscaping tasks.

  • July - September 2028:

    • Handover completed homes to management team and new owners.

    • Set up property management and maintenance teams.

    • Conduct final walkthroughs with new homeowners and address any issues.

Phases 7-12: Repeat for Subsequent Phases (10 Homes Each)

Phase 7: Planning and Preparation for Phase 2 (Oct 2028 - Mar 2029)

Phase 8: Site Engineering and Infrastructure Development for Phase 2 (Apr 2029 - Aug 2029)

Phase 9: Civil Construction for Phase 2 (Sep 2029 - Jun 2030)

Phase 10: Interior Construction and Finishing for Phase 2 (Jul 2030 - Jun 2031)

Phase 11: Landscaping and Farming for Phase 2 (Jul 2031 - Mar 2032)

Phase 12: Final Inspections and Handover for Phase 2 (Apr 2032 - Sep 2032)

(Repeat these phases for subsequent phases until 54 homes are completed.)

Final Summary Timeline

  • Phase 1-6:

    • Planning and Land Acquisition: Oct 2024 - Mar 2025

    • Site Engineering and Infrastructure Development: Apr 2025 - Aug 2025

    • Civil Construction for Phase 1: Sep 2025 - Jun 2026

    • Interior Construction and Finishing for Phase 1: Jul 2026 - Jun 2027

    • Landscaping and Farming for Phase 1: Jul 2027 - Mar 2028

    • Final Inspections and Handover for Phase 1: Apr 2028 - Sep 2028

  • Phase 7-12 (Repeat for each subsequent phase of 10 homes):

    • Planning and Preparation for Phase 2: Oct 2028 - Mar 2029

    • Site Engineering and Infrastructure Development for Phase 2: Apr 2029 - Aug 2029

    • Civil Construction for Phase 2: Sep 2029 - Jun 2030

    • Interior Construction and Finishing for Phase 2: Jul 2030 - Jun 2031

    • Landscaping and Farming for Phase 2: Jul 2031 - Mar 2032

    • Final Inspections and Handover for Phase 2: Apr 2032 - Sep 2032

Key Milestones

  • October 2024: Project initiation

  • April 2025: Start of site engineering

  • September 2025: Break ground on the first homes

  • July 2026: Start of interior construction for Phase 1

  • July 2027: Start of landscaping and farming for Phase 1

  • April 2028: Final inspections begin for Phase 1

  • September 2028: Completion and handover for Phase 1

Completion of Full Project

  • October 2024 - September 2035: Completion of all 54 homes

By following this structured timeline, Harmony Meadows will be developed efficiently and sustainably, ensuring a smooth transition from planning to completion while meeting all environmental and regulatory standards.